🫡 Proxie — Portfolio Dashboard

Live  ·  Sprint 096 (Mar 2–13, 2026)  ·  Last updated: Mar 10, 2026 — 1:10 PM UTC
Active Projects
14
12 ZP · 50 Jira boards
Portfolio Value
$393K
In-progress CRM deals
At Risk
3
BioLab · Brandgenie · BHCo
Unpaid Milestones
$26K+
Overdue or due this month
Team Utilisation
66%
365 hrs idle / 1,072 total
🔴 Critical Risk Projects
BioLab Booking System
PM: Shahbaaz Khan
$128,400
14 done / 250+ tasks Deadline: Jul 10, 2026
⚡ 3.5x overallocated ⚡ 59% still To Do 💰 M3 $19,260 due Mar 28 8 tasks need discussion
PD & Brandgenie
PM: Banka (Ravi)
$72,229
51 done / 100+ tasks (page 1) Deadline: Mar 31
🤒 Aman sick since Mar 1 💰 M5 ~$7K OVERDUE 33 tasks still To Do No replacement assigned
BHCo / Hub Migration
PM: Banka (Ravi)
$1,280
~13 done / 47 tasks Deadline: PAST (Mar 6)
⏰ 4 days past deadline 33 tasks still To Do No revised timeline
🟡 Moderate Risk
Mirror Northcote Site
PM: Garima Mehta
$3,000
1 done / 14 tasks Deadline: Mar 21
⏳ 9 tasks in UAT PM Approval Dev IS done — Garima hasn't reviewed
Attuniq (Scenarios AI)
PM: Shahbaaz Khan
Internal
~47% done · 53 open tasks Real target: ~Jun 2026
👥 Lost 2 devs (Sushil, Vikas) 💸 Budget 2.5x over ($9.9K/$3.8K) Rahul velocity: 2.5%/day
Bounce Chatbot
PM: Banka (Ravi)
$1,600
10 done / 14 tasks Deadline: PAST (Mar 6)
1 task in UAT PM Approval Nearly done — push to close
ASAI AI Podcast
PM: Shahbaaz
$4,880
17 done / 25 tasks Ongoing monthly
6 To Do · 1 dependency blocked
🟢 Tracking / Low Risk
Radio Ad Intelligence
PM: Shahbaaz
$23,400
Early stage Deadline: Jun 5, 2026
Red Tradies AI Shopping
PM: Shahbaaz
$25,000
Just kicked off (Mar 9) No end date set
Nuggts
PM: Shahbaaz
Active
Active dev Deadline: Apr 30
💰 Cashflow — Milestones Due / Overdue
Status Project Milestone Amount Due Action
Overdue PD & Brandgenie M5 ~$7,223 Feb 15 Chase Banka → invoice now
Overdue VA Drupal Resource Dec milestone $4,500 Dec 2025 Confirm with Manasee if invoiced
Overdue VA Magento Resource Dec milestone $4,500 Dec 2025 Confirm with Manasee if invoiced
Due Soon BioLab Booking System M3 $19,260 Mar 28 Flag to Manasee by Mar 25
At Risk PD & Brandgenie M6 (final) ~$7,223 Tied to completion Blocked until Aman returns
Unknown ASAI Podcast Monthly $480 Ongoing Verify current month invoiced
👤 PM Workload Distribution
Shahbaaz Khan
Senior PM — Heaviest load
Active Deals12
Portfolio Value$238K
Key RiskBioLab 3x overalloc
Completed (lifetime)50+
Manasee Vachani
Head of Ops — 7 active deals
Active Deals7
Portfolio Value$22K
On Hold4 ($30K)
StyleCliq-first, no ZP
Banka (Ravi)
PM — 4 active deals
Active Deals4
Portfolio Value$4K
Key RiskBHCo past deadline
StyleResponsive, reactive
Garima Mehta
PM — Lightest load
Active Deals6
Portfolio Value$11K
Key Risk9 tasks in her review queue
Concentration5/12 = PMI
🔥 Sprint 096 — Resource Allocation Heatmap
Kareem
Atomate · In House
371%
234h alloc / 63h avail
Manoj
Laravel · Freelancer
286%
180h alloc / 63h avail
Rahul Singh
Mobile App · In House
137%
86h alloc / 63h avail (46h blocked)
Aman
Laravel · In House
🤒 SICK
68h alloc / 0h working
Ajay
IT Support · In House
111%
70h alloc / 63h avail
Sushil
Project Lead · In House
100%
63h alloc / 63h avail
Pragna
Drupal · In House
89%
56h alloc / 63h avail
Amol
Testing · In House
79%
50h alloc / 63h avail
Adeel
Testing · Freelancer
79%
50h alloc / 63h avail
Zeeshan
WordPress · In House
48%
30h alloc / 63h avail
Sharad
Magento · Freelancer
30%
19h alloc / 63h avail
Vikas
Testing · In House
*Jira
0h sprint / 49h avail · Active on Jira maint
Akhtar
Laravel · In House
0%
0h alloc / 63h avail 🔴 IDLE
Nida
Laravel · In House
0%
0h alloc / 63h avail 🔴 IDLE
Shujaat
Laravel · In House
0%
0h alloc / 63h avail 🔴 IDLE
Imran
Shopify · Freelancer
0%
0h alloc / 63h avail 🔴 IDLE
Samir
Designer · Freelancer
0%
0h alloc / 63h avail 🔴 IDLE
⚡ Priority Actions — This Week
Brandgenie M5 invoice: ~$7K overdue since Feb 15. Chase Banka for status — money is sitting on the table. Banka
Aman replacement: Sick since Mar 1 (typhoid). 68hrs/sprint of PD work stalled. Assign Akhtar (63h idle) immediately. Manasee
BioLab reality check: ZP shows 5.6% complete but sprint allocates 3x capacity. Is ZP being updated? What's actual progress? M3 ($19K) due Mar 28. Shahbaaz
Mirror Northcote: 9 tasks stuck in UAT PM Approval. Dev is done. Garima needs to batch-review this week. Mar 21 deadline. Garima
VA Dec milestones: $9K (Drupal + Magento) marked unpaid since Dec 2025. Were these invoiced? If not, that's 3 months of leaked cashflow. Manasee
BHCo revised timeline: 4 days past deadline, 72% still To Do. Need revised delivery date from Banka. Banka
Idle capacity rebalance: 365 hrs (34% of team) sitting idle while Kareem/Manoj are 3x overloaded. Akhtar, Nida, Shujaat are Laravel — can they take BioLab overflow? Manasee
Bounce Chatbot: 71% done. 1 UAT task left. Push to close and mark complete this week. Banka
🧠 Systemic Insights
ZP Staleness is Systemic

Work happens in Cliq standups but Zoho Projects tasks don't get updated. Affects all PMs. Sprint sheet ≠ ZP ≠ Jira ≠ reality. No single source of truth for project progress.

CRM Data Quality is Poor

84% of active deals have no Project_End_Date. 18 zombie deals past end date still "In Progress". Missing PMs, null milestone amounts, stale maintenance records inflating counts.

Sprint Sheet is a Wishlist

Manual Zoho Sheet — not linked to Jira or ZP. Over-allocation numbers (BioLab 398h for 126h available) suggest it lists all upcoming work, not constrained sprint plans. No velocity tracking.

Invoice-Milestone Gap

$26K in completed deals have "unpaid" milestones (likely invoiced externally but never updated in CRM). 12 orphaned milestones ($54K) not linked to any deal. System doesn't reflect cashflow reality.